Below are several of the projects and construction works in which Inaccés has participated and that we feel are interesting to mention for their uniqueness, their technical difficulty, their complexity of implementation by the application of innovative systems, or their significance for society as a whole.

Strengthening of the tunnel vault, removal of the most unstable material, and strengthening of the rest with bolts and reinforced concrete designed with wire mesh.
Location: Autopista C-32 Túnel 4 (Barcelona).
Year: 2010

Protection against falling blocks with mesh and bolts in a mine gallery.
Location: Gualba.
Year: 2015

Waterproofing the tunnel by placing waterproof sheet.
Location: Túnel del Cremallera de Montserrat.
Year: 2003

Strengthening of the tunnel vault by means of bolts, d = 25 mm and 3 metres in length, wire mesh and sprayed concrete.
Location: Túnel de Erga. Autovía Leizarán.
Year: 2007
2014
Martinet (Girona)
Stabilization of the gallery and slopes at the Cabiscol II hydroelectric power station.
2014
Barcelona
Strengthening of the support for Vallvidriera tunnels’ service gallery
2014
El Figaró (Barcelona)
Strengthening the support of the Tunnel del Figaró on the C-17.
2014
Súria (Barcelona)
Slope strengthening in Súria mines. Súria (Barcelona);
2013
Aduna (Guipuzcoa)
Strengthening the grouting of the Tunnel de Aduna and of the Basque Country’s new railway network
2013
Súria (Barcelona)
Slope treatment at the Iberpotash mining facilities.
2012
El Bruc (Barcelona)
Slope stabilization in the mouth of the tunnel del Bruc, N-II
2012
Alp (Girona)
Strengthening the support of the Tunnel del Cadí
2011
Irurzun (Navarra)
Strengthening Irurzun tunnel
2011
El Bruc (Barcelona)
Strengthening the tunnel del Bruc, on the N-II
2011
Barcelona
Strengthening the tunnel de l’Obaga Negre
2011
Manresa (Barcelona)
Strengthening the tunnel de Gomis, FFCC Martorell-Manresa line
2011
Queralbs (Girona)
Strengthening the Queralbs underpass station
2010
Barcelona
Reinforcement of the support of tunnel 4 of C-32 motorway.. Maresme
2008
Queralbs (Girona)
Strengthening in various areas in the construction of Roc del Dui tunnel, the Vall de Núria Rack Railway
2008
Vielha (Lleida)
Strengthening of the support in various areas of the Vielha tunnel.
We unite processes, leading technologies and talented individuals focused on safety
Conditioning slopes on the N-260 road. - This action is part of the project of the Ministry of Transport, Mobility,… + read more
The vital importance of installing rockfall barriers on railway tracks. - Safety is one of the most critical aspects in railway transportation. In the… + read more
First 9,000 KJ dynamic barrier set up in the Iberian Peninsula. - At the end of last year, INACCÉS completed the installation of the first… + read more
Emergency work due to the detachment of a retaining wall on the Sa Calobra road - The Ma-2141 road, an emblematic road of the Serra de Tramuntana, suffered a… + read more
Inaccés Geotècnica Vertical, S.L., offers services of slope and ground stabilization and reinforcement, and protection against rockfalls and avalanches even in areas with extreme access.